Michigan

Active Bans / Moratoriums

Michigan introduced a bipartisan House bill package (HB 5594-5596) proposing a one-year moratorium preventing EGLE and local governments from issuing data center permits until April 2027. Governor Whitmer has explicitly stated she would veto any moratorium legislation, calling it 'an automatic non-starter.' More than 20 Michigan townships and cities have enacted local moratoria independently — the most of any state — with Meridian Township, Macomb County's Washington Township, and the City of Flint (a one-year pause on June 8, 2026) among the most recent. In June 2026 legislators renewed the statewide push: HB 5594-5596 (House) and companion SB 1018-1020 (Senate) were introduced to halt data center development until April 1, 2027, and Senate Democrats unveiled a separate eight-bill regulatory package — though none has been enacted. On July 15, 2026 Governor Whitmer unveiled the Michigan Affordable and Responsible Growth Action Plan, pairing a call for lawmakers to codify consumer and energy-cost guardrails in statute with a voluntary industry pledge — residents never pay for data center energy demand, companies build or buy additional energy resources, grid reliability and freshwater protection commitments, and jobs and community benefits. Google and Oracle announced support the same day. Whitmer continues to oppose a statewide moratorium. Kalamazoo's City Commission approved a resolution on August 18, 2026 enacting a one-year data center moratorium, with the community divided over whether the temporary pause should become a permanent ban. Bay City's planning commission formed a subcommittee on August 20 to study a draft ordinance addressing facility size, power demand, water use, noise and decommissioning, with a revisit scheduled for October.

Legislation

BillTitleStatus
HB 5594-5596Data Center Development Moratorium (until April 1, 2027)Introduced June 2026 — referred to House Government Operations
SB 1018-1020Data Center Moratorium (Senate companion)Introduced June 2026 — Senate Government Operations
HB 4521Data Center Permit Moratorium ActIn committee
Michigan Affordable and Responsible Growth Action PlanExecutive plan: legislative ask to codify ratepayer/energy-cost guardrails plus a voluntary data center industry pledgeAnnounced by Gov. Whitmer — July 15, 2026 (Google and Oracle signed on)

Local Actions

29active bans
15of 83 counties (18%)
City of Flint
activemoratorium

City Council voted 7-1 on June 8, 2026 for a one-year moratorium on data centers amid public outcry.

2026-06-08View source →
City of Northville
activemoratorium

12-month moratorium on all data centers (preemptive).

2026-01-06View source →
Springfield Township
activemoratorium

180-day moratorium. Triggered by 84-acre proposed campus.

2026-01-07View source →
City of Pontiac
activemoratorium

6-month moratorium on all data centers.

2026-01-21View source →
City of Sterling Heights
activemoratorium

1-year moratorium on all data centers.

2026-02-04View source →
City of Detroit
proposedmoratorium

City Council approved a resolution opposing unrestricted use of Detroit water for AI data center cooling and calling for consumption monitoring and environmental safeguards. The City Planning Commission is developing a Detroit-specific regulatory framework; the mayor remains undecided on a moratorium.

2026-07-22View source →
Ypsilanti Township / YCUA
activemoratorium

Ypsilanti Community Utilities Authority (YCUA) unanimously approved a 12-month moratorium on providing water and sewer services to new data centers on April 22/23, 2026. Township Board had passed a resolution April 15 requesting the move. Prompted by a proposed $1.2B University of Michigan data center and Thor Equities' $1B proposal (potentially 1M gallons/day water demand).

2026-04-22View source →
City of Ypsilanti
activemoratorium

60-day emergency moratorium + 365-day resolution on all data centers (preemptive). 57 resident emails in support.

2026-03-03View source →
City of East Lansing
activemoratorium

6-month moratorium on all data centers (preemptive, no proposals pending).

2026-03-17View source →
Howell Township
expiredmoratorium

6-month moratorium (expired). Triggered by $1B Meta hyperscale campus proposal on 1,000+ acres.

2025-11-21View source →
City of Mason
expiredmoratorium

Moratorium enacted, lifted 2/3/2026 after M-3 zoning adopted. Suspended by citizen petition (755 signatures) on 3/2.

2026-01-06View source →
Armada Township
activemoratorium

180-day moratorium on data center development

2026-01-14View source →
Dundee Township
activemoratorium

90-day moratorium, subsequently extended

2025-10-01View source →
Grand Blanc Township
activemoratorium

1-year moratorium on data center development

2026-01-21View source →
Green Charter Township
activemoratorium

1-year moratorium on data center development

2025-12-09View source →
Hayes Township
activemoratorium

180-day moratorium on data center development

2026-02-10View source →
Lenox Township
activemoratorium

4-month moratorium with extension option

2026-02-02View source →
Lodi Township
activemoratorium

180-day moratorium on data center development

2026-02-03View source →
Manchester Township
activemoratorium

2-year moratorium on data center development

2025-10-14View source →
Pittsfield Township
activemoratorium

180-day moratorium on data center development

2025-11-18View source →
City of Saginaw
activemoratorium

6-month moratorium, unanimous vote

2026-01-13View source →
City of Saline
activemoratorium

12-month moratorium on data center development

2026-01-12View source →
City of South Lyon
activemoratorium

12-month moratorium on data center development

2026-02-01View source →
Sylvan Township
activemoratorium

6-month moratorium on data center development

2026-01-01View source →
City of Taylor
activemoratorium

1-year moratorium on data center development

2026-01-01View source →
Tyrone Township
activemoratorium

6-month moratorium on data center development

2026-01-01View source →
Ann Arbor Township
activemoratorium

12-month moratorium on data center development

2026-02-01View source →
Erie Township
activemoratorium

Limited moratorium on data center development

2026-02-10View source →
Delta County
proposedmoratorium

Planning Commission approved moratorium draft for up to 12 months, sent to legal review

2026-04-07View source →
Meridian Township
activemoratorium

Board voted unanimously on May 19, 2026 for a six-month moratorium on building or approving data centers and battery storage while it develops a regulatory framework.

2026-05-19View source →
Washington Township (Macomb County)
activemoratorium

Board of Trustees passed a six-month moratorium on accepting and reviewing data center applications pending zoning changes.

2026-05-23View source →
Haring Township
activemoratorium

Township board voted unanimously for a six-month moratorium on data center construction after a large turnout of residents in opposition.

2026-07-14View source →
City of Kalamazoo
proposedmoratorium

City commissioners are weighing a temporary moratorium on new data center proposals; the commission is set to revisit the question in roughly three weeks after the city attorney presents regulatory options.

2026-07-22View source →
City of Kalamazoo
activemoratorium

City Commission approved a resolution enacting a one-year moratorium on data center development. Residents are divided over whether to make the pause a permanent ban.

2026-08-18View source →
City of Bay City
proposedzoning restriction

Planning commission formed a subcommittee to study a draft data center ordinance covering facility size, power demand, water use, noise and decommissioning. Revisit scheduled for October 2026.

2026-08-20View source →